When you schedule a job there can only be one job doing one task. However, there will be times where you need to perform the same operation on a lot of objects. To do this, use a ParallelFor job type, which inherits from IJobParallelFor
.
A ParallelFor job uses a NativeArray
of data to act on as its data source. ParallelFor jobs run across multiple CPU cores. There’s one job per core, with each handling a subset of the workload.
IJobParallelFor
behaves like IJob
, but instead of a single Execute
method, it invokes the Execute
method once per item in the data source. There’s also an integer parameter index in the Execute
method, which you can use to access and operate on a single element of the data source within the job implementation.
The following is an example of a ParallelFor job definition:
struct IncrementByDeltaTimeJob: IJobParallelFor
{
public NativeArray<float> values;
public float deltaTime;
public void Execute (int index)
{
float temp = values[index];
temp += deltaTime;
values[index] = temp;
}
}
To schedule a ParallelFor
job, you must specify the length of the NativeArray
data source that you want to split. The job system doesn’t know which NativeArray
you want to use as the data source if there are several in the struct. The length also tells the job system how many Execute
methods to expect.
In Unity’s native code, the scheduling of ParallelFor
jobs is more complicated. When Unity schedules a ParallelFor
job, the job system divides the work into batches to distribute between cores. Each batch contains a subset of Execute
methods. The job system then schedules one job in Unity’s native job system per CPU core and passes that native job to the batches to complete.
When a native job completes its batches before others, it steals remaining batches from the other native jobs. It only steals half of a native job’s remaining batches at a time, to ensure cache locality.
To optimize the process, you need to specify a batch count. The batch count controls how many jobs you get, and how fine-grained the redistribution of work between threads is. Having a low batch count, such as 1, gives you an even distribution of work between threads. However, it comes with some overhead, so sometimes it’s better to increase the batch count. Starting at 1 and increasing the batch count until there are negligible performance gains is a good strategy.
The following is an example of scheduling a ParallelFor job
Job code:
// 2 つの浮動小数点の値を加算するジョブ
public struct MyParallelJob : IJobParallelFor
{
[ReadOnly]
public NativeArray<float> a;
[ReadOnly]
public NativeArray<float> b;
public NativeArray<float> result;
public void Execute(int i)
{
result[i] = a[i] + b[i];
}
}
Main thread code:
NativeArray<float> a = new NativeArray<float>(2, Allocator.TempJob);
NativeArray<float> b = new NativeArray<float>(2, Allocator.TempJob);
NativeArray<float> result = new NativeArray<float>(2, Allocator.TempJob);
a[0] = 1.1;
b[0] = 2.2;
a[1] = 3.3;
b[1] = 4.4;
MyParallelJob jobData = new MyParallelJob();
jobData.a = a;
jobData.b = b;
jobData.result = result;
// 結果の配列の各インデックスに 1 つずつの実行と、各バッチ処理に 1 要素をもつジョブをスケジュールします
JobHandle handle = jobData.Schedule(result.Length, 1);
// ジョブが完了するのを待機します
handle.Complete();
// 配列に割り当てられたメモリを開放します
a.Dispose();
b.Dispose();
result.Dispose();
A ParallelForTransform
job is another type of ParallelFor
job designed specifically for operating on Transforms. It’s useful for working on Transform operations from jobs efficiently. For more information, see the ParallelForTransform API documentation.